Question: Andrea Johnson is working on a project. The table below lists the tasks, together with the predecessors and duration for each task. State your answer
Andrea Johnson is working on a project. The table below lists the tasks, together with the predecessors and duration for each task. State your answer clearly.
- Draw a network diagram for the project
- Determine the tasks on the critical path? Write down the names of the tasks on the critical path.
- What is the expected duration of this project? write down your answer
| TASK | IMMEDIATE PREDECESSOR(S) | TIME (DAYS) |
| A | - | 4 |
| B | A | 3 |
| C | A | 6 |
| D | B | 5 |
| E | B | 6 |
| F | C | 7 |
| G | E,F | 2 |
| H | D | 4 |
| I | G,H | 5 |