Question: Anju Chaudhary is developing a program in leadership training for middle-level managers. She has listed a number of activities that must be completed before a

Anju Chaudhary is developing a program in
Anju Chaudhary is developing a program in leadership training for middle-level managers. She has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A 2 B 5 1 D B 10 E AD 3 F 6 G E, F 8 a. Develop an AON network for this problem. b. What is the critical path? c. What are the non-critical activities