Anju Chaudhary is developing a program in supply chain management certification for managers. She has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table. Activity Immediate Predecessor(s) Time (days)
A -10
B -6
C -3
D B 2
E A, D 3
F C 5
G E, F 12
Slack time for each of the activities is: