Question: answer 68.625 is incorrect Wagons are assembled in a process with two rsources. The first resource has a capacity of 33 wagons per hour. The
answer 68.625 is incorrect
Wagons are assembled in a process with two rsources. The first resource has a capacity of 33 wagons per hour. The capacity of the second resource is 36 wagons per hour. The first resource has 1 worker and the second resource has 6 workers. One additional worker is hired who is as productive as the current workers. Instruction: Round your answer to three decimal places. What is the new capacity of this process? wagons per hour