Question: answer a only 43. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error)
43. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error) (a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. (6) Fill in the table on the next page to determine the carliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack - LS-ES or LF-EF. Activity Time (days) Immediate Predecessor(s) A 12 B 14 A,B 9 D B 5 E 6 F CD 9 G E 18 H E, F 5 A E G Finish Start B D F H