Question: answer A through C You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project A B Year 0 = $52 - $100 Year 1 $24 $21 Year 2 $22 $41 Year 3 $21 $48 Year 4 $14. $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.3%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently