Question: answer above The requirement for testing cannot be completed any earlier than four days after the prototype is built is best represented by? Start-to-start with

answer above The requirement for testing cannotanswer above

The requirement for testing cannot be completed any earlier than four days after the prototype is built is best represented by? Start-to-start with lag Finish-to-start with lag Finish-to-Finish with lag Start-to-Start with lag