Question: Answer all question based on the picture given. Thank you Answer all 10 Question based on the picture given. 1. The value of salvaged fixed
Answer all question based on the picture given. Thank you

Answer all 10 Question based on the picture given.
1. The value of salvaged fixed asset at the final year of the project is RM___________.
2. Terminal Value of the project is RM__________.
3. Total Present Value is RM___________.
4. Total FV of the project is RM___________.
5. Payback Period: __________
6. Discounted payback period: _______
7. NPV is RM__________.
8. IRR is _________%.
9. MIRR is ________%
10. PI is _________.
Project Xenus Project Xenus Project cost Operating Cash Flows Cost of capital 1,800,000.00 1 1,000,000.00 2 600,000.00 3 500,000.00 4 650,000.00 6.32% Details 50% is fixed assets' cost that 50% can be salvaged at the end of the project