Question: Answer all questions 1) The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project. Group of answer choices Network Assumption

Answer all questions

1) The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project.

Group of answer choices

Network

Assumption log

Project management system

Imposed date

2) Communication methods

Group of answer choices

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A point at which dependency lines connect on a schedule network diagram.

A systematic procedure, technique, or process used to transfer information among project stakeholders.

A graphical representation of the logical relationships and timing among the work activities.

3) Communication models

Group of answer choices

A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller's costs.

The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

A description, analogy, or schematic used to represent how the communication process will be performed for the project.

A category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality.

4) Data representation techniques

Group of answer choices

The evaluation of whether or not a product, service, or result complies with a regulation, requirement, specification, or imposed condition. Contrast with validation.

A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (for example, feeding buffer, resource buffer) to provide further detail on what types of risk are meant to be mitigated.

Graphic representations or other methods used to convey data and information.

A systematic procedure, technique, or process used to transfer information among project stakeholders.

5) Change log

Group of answer choices

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.

A collection of logically related project activities that culminates in the completion of one or more deliverables.

A comprehensive list of changes submitted during the project and their current status.

The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!