Question: Answer ALL questions using the information below. The highway project in Section B has now been approved for further detailed planning and design by the
Answer ALL questions using the information below.
The highway project in Section B has now been approved for further detailed planning and design by the GOJ. However, the residents in the towns of Ulster Spring, Joe Hut and Albert Town are concerned that the roadway may negatively affect their local businesses during construction throughtraffic obstruction, noise and dust levels.
This projects budget at $ and its cost data for four major activities are shown below:
Activities PV$ Complete Actual Cost $
A
B
C
Note show all answers to decimal places.
In light of these concerns, outline and explain three opportunities that the project manager can present to the residents of these towns. marks
What relationship between project risks and cost of changes for the research project might be expected in its life cycle? marks
Calculate the cost variance CV and cost performance index CPI for the project. marks
This projects budget is $Calculate the estimate at completion EAC for the project.
mark
What is the variance at completion VAC mark
What can you say about the cost performance of the project? mark
The contractor reduces the original planned value of activity C by a half, and completes of the work.
What is the schedule performance index SPI of activity C with the contractors reduction? marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock