Question: Answer all the following question: Mr. Khalid has a car wash service center in Jubail. He wants to service 25 cars per day with 8

Answer all the following question:

  1. Mr. Khalid has a car wash service center in Jubail. He wants to service 25 cars per day with 8 working hours/day. The tasks, task times, and immediate predecessors for washing one car is given below: (Write the formulae and use two places after the decimal point) (8.5 marks)
    1. What is the cycle time for his operations? (1.5 marks)
    2. How many minimum (theoretically) number of workstations are required by Mr. Khalid? (1.5 marks)
    3. The goal of Mr. Khalid is to have an optimal efficiency. Hence, compute and inform Mr. Khalid on the efficiency based on the practical balancing of workstations? (2.25 marks)

Tasks

Performance Time (Minutes)

Task must follow task listed below

A

3

-

B

9

-

C

11

A, B

D

6

B, C

E

9

A

F

6

D, E

G

5

E, F

>> PLEASE write your own answer and DO NOT plagiarize it

if you answer it correctly I will be pleased to give you LIKE

THANK YOU AND HAVE A LOVELY DAY!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!