Question: Answer all the following question: Mr. Khalid has a car wash service center in Jubail. He wants to service 25 cars per day with 8
Answer all the following question:
- Mr. Khalid has a car wash service center in Jubail. He wants to service 25 cars per day with 8 working hours/day. The tasks, task times, and immediate predecessors for washing one car is given below: (Write the formulae and use two places after the decimal point) (8.5 marks)
- What is the cycle time for his operations? (1.5 marks)
- How many minimum (theoretically) number of workstations are required by Mr. Khalid? (1.5 marks)
- The goal of Mr. Khalid is to have an optimal efficiency. Hence, compute and inform Mr. Khalid on the efficiency based on the practical balancing of workstations? (2.25 marks)
| Tasks | Performance Time (Minutes) | Task must follow task listed below |
| A | 3 | - |
| B | 9 | - |
| C | 11 | A, B |
| D | 6 | B, C |
| E | 9 | A |
| F | 6 | D, E |
| G | 5 | E, F |
>> PLEASE write your own answer and DO NOT plagiarize it
if you answer it correctly I will be pleased to give you LIKE
THANK YOU AND HAVE A LOVELY DAY!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock