Question: Answer ANY THREE ( 3 ) questions in this section. Important note - Questions that require diagrams can be answered on a Word document and
Answer ANY THREE questions in this section.
Important note Questions that require diagrams can be answered on a Word document and submitted as a file upload on MANCOSA Connect. Ensure that your answers are clearly labelled.
QUESTION
Marks
Piet Morroy is the project manager for the Gautrain project, a highspeed railway system implemented in Gauteng, South Africa. It represents a significant transportation infrastructure initiative aimed at improving connectivity, reducing congestion, and enhancing mobility within the Gauteng province, which includes Johannesburg, Pretoria and surrounding areas. The following table is provided illustrating the activities of the project.
tableActivityPreceding,tableOptimisticTimetableProbableTimetablePessimisticTimetableExpectedTime daysABACADAEBFBGC FHDIHJG I,KE J
Using the provided information above, determine the following:
The activities that cannot be delayed and the expected time for completing the project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock