Question: Answer: Can the project be completed in 25 days? Calculate LS, LF. Show your calculations on the network diagram. Select one: a. No b. Yes

 Answer: Can the project be completed in 25 days? Calculate LS,LF. Show your calculations on the network diagram. Select one: a. Nob. Yes Which activities are on the critical path? Calculate the slack

Answer: Can the project be completed in 25 days? Calculate LS, LF. Show your calculations on the network diagram. Select one: a. No b. Yes Which activities are on the critical path? Calculate the slack value to answer the question above. Show your work on the network diagram. Select one: a. ABEHI b. ABDG1 c. ACFHI d. ABEGI