Question: answer choices: A. 7.5 hours B. 5 hours C. 3 hours D. 2.5 hours E. 2 hours The owner/operator of the local franchise of Handyman,
answer choices:
A. 7.5 hours
B. 5 hours
C. 3 hours
D. 2.5 hours
E. 2 hours
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received Due Processing Time (hrs) (hre from now) Job W N = X = 2 NW NU 2 2 2 If he uses the first come first served priority rule to schedule these jobs, what will be the average completion time? Multiple Choice 75 hours