Question: Answer Consider the network below. Activity durations are given in nodes. What is finish time of the project? C,4 F,7 H,8 A,4 D,6 G,7 K,4

Answer

Answer Consider the network below. Activity durations are given in nodes. What

Consider the network below. Activity durations are given in nodes. What is finish time of the project? C,4 F,7 H,8 A,4 D,6 G,7 K,4 B,5 E,9 J,10 Select one: O a. 28 O b. 29 O c. 30 O d. 32