Question: Answer correct only. Given the data in the spreadsheet below, what is the probability of completing the critical path of the project in 46.32 time

Answer correct only.
Answer correct only. Given the data in the
Given the data in the spreadsheet below, what is the probability of completing the critical path of the project in 46.32 time units or less? Activity 4 Preceded By None None A and B Optimistic Time 12.65 12.54 12.99 14.69 13.16 Most Likely Time 14.03 14.05 14.89 17.12 14.6 Pessimistic Time 17.69 16.95 17.48 20.97 18.51

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!