Question: Answer correct pls. Consider the following PERT network with activity times in parenthesis in front of each activity. C (4) Start | A (3) B

Answer correct pls.

Answer correct pls. Consider the following PERT

Consider the following PERT network with activity times in parenthesis in front of each activity. C (4) Start | A (3) B (2) F (5) Finish D (3) E (6) The [ES, EF] for activity Care (5,9) and for activity D are [5,8]. What is the earliest finish time for activity F? a 14 O c. 8 d.5