Question: Answer D please Thanks so much 2) (6 points) Draw the CPM network and determine the completion time, the critical path and the slack times
Answer D please
Thanks so much
2) (6 points) Draw the CPM network and determine the completion time, the critical path and the slack times for this project. a) Completion Time =25 Days b) Critical Path is _B, D, G, J_, c) Fill in slack times on table. d) If you could (magically) cut any activity time in half with the goal of decreasing the overall project completion time as much as possible, which activity should you cut and what would be the new project completion time