Question: answer @ ezto.mheducation.com M Questio... Final Exam- Fall 2024 Saved Help Save & Exit Submit 2 8 In precedence network analysis, knowing the slack time

answer

answer @ ezto.mheducation.com M Questio... Final
@ ezto.mheducation.com M Questio... Final Exam- Fall 2024 Saved Help Save & Exit Submit 2 8 In precedence network analysis, knowing the slack time allows managers to: Multiple Choice O extent the project if necessary. increase the critical path. pay attention to activities that could delay the project. delay critical activities. OO RO N C decrease the project duration. %