Question: answer in excel sheet Q.2 Find the position for each job by using Johnson's rule. We use the following four step process to find the
Q.2 Find the position for each job by using Johnson's rule. We use the following four step process to find the optimal sequence. Step 1: Find the minimum processing time considering times on both machines. Step 2: Identify the corresponding job and the corresponding machine for the minimum time identified at Step 1. Step 3: Schedulling Rule (M2, A) (1,2,3,4) I (a) If the machine identified in Step 2 is machine M1 then the job identified in Step 2 will be scheduled in the first available schedule position. (b) If the machine identified in Step 2 is machine M2 then the job identified in Step 2 will be scheduled in the last available schedule position. Step 4: Remove the job from consideration whose position has been fixed in Step 3; and go to Step 1. Continue this process until all jobs have been scheduled
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts