Question: Answer is bolded below. Please provide detailed explanation on how to solve this. Thank you. 4. ELO Construction Co. began operations in 2015. Construction activity
Answer is bolded below. Please provide detailed explanation on how to solve this. Thank you.
4. ELO Construction Co. began operations in 2015. Construction activity for 2015 is shown below. ELO uses the completed-contract method.
| Contract | Contract Price | Billings Through 12/31/15 | Collections Through 12/31/15 | Costs to 12/31/15 | Estimated Costs to Complete |
| 1 | $4,650,000 | $4,450,000 | $3,900,000 | $3,700,000 | - |
| 2 | 3,600,000 | 1,800,000 | 1,600,000 | 870,000 | $2,030,000 |
| 3 | 3,100,000 | 1,860,000 | 1,600,000 | 1,680,000 | 1,120,000 |
What amount of gross profit should be reported on the income statement for 2015?
$0
$1,340,000
$950,000
$1,480,000
5. Reedy Builders, Inc. is using the completed-contract method for a $12,400,000 contract that will take three years to complete. Data at December 31, 2015, the end of the first year, are as follows:
| Costs incurred to date | $5,200,000 |
| Estimated costs to complete | 7,800,000 |
| Billings to date | 4,920,000 |
| Collections to date | 4,540,000 |
The gross profit or loss that should be recognized for 2015 is
a $600,000 loss.
$0.
a $240,000 loss.
a $200,000 loss.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
