Question: Answer is provided, please go through step by step so I can fully understand how to solve. please show me all calculations so I can

Answer is provided, please go through step by step so I can fully understand how to solve. please show me all calculations so I can easily follow along. thank you
25) A project is expected to create operating cash flows of $68,300 a year for 3 years. The initial cost of the fixed assets is $80,000. These assets will be worthless at the end of the project. An additional $6,000 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 14%? A) $76,617.30 B) $73,408.18 C) $78,567.47 D) $72.567.47 E) S79,200.03
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts