Question: Answer One ( 1 ) Question from Section B Question 4 Kam Limited manufacture a single product and operates a standard costing system. The following

Answer One (1) Question from Section B Question 4 Kam Limited manufacture a single product and operates a standard costing system. The following data is available: Budgeted Data (per unit): Materials 10kgs Material cost per kg 11.50 Labour 6 hours Labour cost per hour 8.00 Budgeted production for August was expected to reach 10000 units, however 9500 units were actually produced. The actual costs incurred were as follows: Materials Labour Required: 94000 kgs at 12.00 per kg 50000 hrs at 8.50 per hr 1) Calculate the following variances and indicate if the variances are favourable or unfavourable: a) material price b) material usage c) total material variance d) labour rate e) labour efficiency f) total labour variance g) total variance (2 marks for a) to f),1 mark for g), total 13 marks)2) Suggest possible reasons for the material and labour variances calculated. (5 marks)3) Define and briefly explain four (4) limitations of a standard costing system. (4 marks)4) In standard costing there are three different levels of standard cost. Briefly explain these different levels.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!