Question: Answer Options: A) 31 B) 27 C) 32 D) 28 E) 33 Given the information below, how long is the Critical Path? Activity Time Immediate

Answer Options:
A) 31
B) 27
C) 32
D) 28
E) 33
Given the information below, how long is the Critical Path? Activity Time Immediate Predecessor A 2 B 1 Ic C 5 A D 4 B E 7 IC, D F. 2 E G 9 I F 5 G H 27 DStep by Step Solution