Question: Answer Part A Urgent Please Using the intermediate COCOMO model values given in the above tables, (0) Estimate the time required to complete the project
Answer Part A Urgent Please 

Using the intermediate COCOMO model values given in the above tables, (0) Estimate the time required to complete the project using both the pool of developers. [12] (ii) Estimate the number of people required to complete the project. [4] (iii) Analyse the impact of hiring all developers from one or the other pool. [3] Q4 (a) Al Zahra software company, Muscat has recently received an order from an air bag manufacturing company to develop a code using programming language to control the functioning of the air bag. The size of the code is estimated to be 3100 LOC. The reliability of the product is very high and complexity of the product is nominal. The company has a set of developers who have (a) high application experience and low experience in C programming language and (b) low application experience and very high experience in C programming language. The project manager has a choice of hiring from two set of developers. Table 4.1: Intermediate COCOMO values Project aj C di 3.2 bi 1.05 1.12 Organic Semidetached Embedded 2.5 0.38 0.35 3.0 2.5 2.8 1.20 25 0.32 Cost Drivers Table 4.2: Multiplier Values for Effort Calculations Ratings High Very high Extra high Very low low Nominal Product Attributes RELY 0.75 0.88 1.00 1.15 1.40 CPLX 0.70 0.85 1.00 1.15 1.30 1.65 Personal Attributes LEXP 1.14 1.07 1.00 0.95 PCAP 1.42 1.17 1.00 0.86 0.70
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts