Question: Answer Q10-Q12 based on the network diagram given below. B=3 E=7 5 1 G=2 C=5 6 A=6 F=8 D=4 3. Q10- What is the critical

Answer Q10-Q12 based on the network diagram given

Answer Q10-Q12 based on the network diagram given below. B=3 E=7 5 1 G=2 C=5 6 A=6 F=8 D=4 3. Q10- What is the critical path(s) of the project? Q11- What is the total completion time of the project? Q12- Which activity or activities have a slack (float) of 4 units of time? 1 Yeni Microsoft Offic