Question: Answer questions 10-11 using the following figure and table below. Today you sent a note to your boss, the director of project management, stating that

Answer questions 10-11 using the following figure and table below. Today you sent a note to your boss, the director of project management, stating that the data science project would require thirteen weeks for completion. After noticing the customer's desire for quicker completion of the job, you engaged in discussions with the functional managers. As a result of these discussions, you created the table that is displayed below. ( Time = weeks ) Suppose your answer to previous question give you the same additional minimum cost for both an eight-week and a nine-week project. What factors would you consider before deciding whether to do it in eight or nine weeks