Question: answer quick please! In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian fok's construction project and
answer quick please!

In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian fok's construction project and on the right the precedence network is shown The project length is weeks The activities on the critical path are