Question: Answer quickly and correctly for guaranteed thums up. 1 point The cost baseline is calculated as. the sum of all work package cost estimates +

Answer quickly and correctly for guaranteed thums up. Answer quickly and correctly for guaranteed thums up. 1 point The cost

1 point The cost baseline is calculated as. the sum of all work package cost estimates + management reserves the sum of all work package cost estimates + contingency reserves the sum of all work package cost estimates + contingency reserves + management reserves. the sum of all work package cost estimates