Question: ( ANSWER THE BLANKS I DONT HAVE FILLED OUT, I KNOW THOSE ARE CORRET ) A manager wants to assign tasks to workstations in order
ANSWER THE BLANKS I DONT HAVE FILLED OUT, I KNOW THOSE ARE CORRET A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The department uses a
working time of minutes per hour.
a Assign the tasks shown in the above precedence network times are on the nodes and are in minutes to workstations using the
following heuristic rules: i "Assign the task with the largest positional weight." ii Tiebreaker: "Assign the task with the longest time." If
a tie still exists, choose randomly. Do not leave any empty spaces; input a wherever it is required.
b What is the efficiency? Do not round intermediate calculations. Round the final answer to decimal place.
EfficiencyAN
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock