Question: Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S. State the validity along with respective

Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S.

State the validity along with respective reasons:

1.Amount of time by which the actual completion of A can exceed its earliest expected time of completion without any delay of the project.

2.Latest start time minus earliest start time of A.

3.Value by which A can be delayed beyond its earliest start point without affecting earliest start time of S.

4.Latest finish time of A minus earliest start time of S.

5. Resource leveling aims at smoothening of the resource usage rate without changing the project duration.

6.Two actvities have common predecessor and successor activities. So, they can have common initial and final nodes.

7.In respect of any activity whether real or dummy, the terminal node should bear a number higher than the initial node number.

8.The optimal duration of a project is the minimum time in which it can be completed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!