Question: Answer the following Mcq's with reference to MS project Carole Poland is the project manager for an IT company in Ontario, Canada. She receives a

Answer the following Mcq's with reference to MS project

Carole Poland is the project manager for an IT company in Ontario, Canada. She receives a request from the project sponsor to change some formatting for the timeline in MS Project. The project sponsor would like Carole to add a second timeline bar.

Which of the following is the most efficient first step for adding a second timeline bar to the timeline view?

On the Format tab, in the Insert group, click Existing tasks.

On the View tab, in the Task Views group, click Network Diagram.

Click anywhere in the Timeline view.

On the Format tab, in the Insert group, click Timeline Bar.

Amir was originally assigned to a Fixed Duration Task that was estimated to take 3d of Duration to complete. This equates to 24 hours of Work at 100%. Amir has reported that it will take him 32 hours to complete the task. What happens to Duration, Work, and Units when the hours of Work is changed to 32 hours and you press OK. What does the red man indicator mean?

Duration =2d, Work =32hours, Units =200% Amir is crazy.

Duration =3d Work =24 h, Units = 100% Amir gets the job done.

Duration =3d, Work =32h, Units =133% Amir is overallocated

Duration =4d, Work =32hours, Units =100% Amir is not overallocated

An interim plan is different than a baseline plan. In fact throughout your project you may want to save several interim plans without updating the baseline. At which of the following times is it appropriate to save a baseline instead of an interim plan.

:

At the conclusion of a major phase of work

When major changes to the plan have rendered the current baseline invalid.

At preset time intervals such as weekly or monthly

Just prior to entering a large number of actual values

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!