Question: answer the following MCQs without explanation- a) Cycle Time can be shortened for an Assembly Line using-_____- worstations Select one: a. Virtual b. Real c.
answer the following MCQs without explanation-
a) Cycle Time can be shortened for an Assembly Line using-_____- worstations
Select one:
a. Virtual
b. Real
c. Parallel
d. Sequential
b)Under CPM and 3 activity Time estimates, how do we calculate Expected time
Select one:
a. Average of Optimistic (O), Most likely() and pessimistic(P) times
b. Average of O + 6 L + P
C. Average of O + 4 L+ P
d. Average of 20 + 2 L + 2 P
c)At the completion of the forward and backward passes,in Project Scheduling, the slack for an activity is given by the _____
Select one:
a. Difference between early start and harly finish
b. Difference between early start and latest finish
c. Difference between latest start and early finish
d. Amount of idle labor on the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts