Question: Answer the following questions based on the below Critical Path Method (CPM) diagram. (a) Define the term Critical Path. (b) For this project, what is

Answer the following questions based on the below Critical Path Method (CPM) diagram.
(a) Define the term "Critical Path."
(b) For this project, what is the Critical Path?
(c) What is the length of the project (assume the durations are in days)?
(d) What is the Early Finish (EF) of Activity "F"?
(e) What is the Late Finish (LF) of Activity "E"?
(f) What is the Total Float (TF) of Activity "C"?