Question: Answer the following questions for the given Time-Scaled CPM Network: The LS for activity N is: a. 14 b. 13 c. 12 d. 11 e.
Answer the following questions for the given Time-Scaled CPM Network:

The LS for activity N is: a. 14 b. 13 c. 12 d. 11 e. None of the above.
The FF for activity J is: a. 0 b. 4 c. 3 e. 1 f. 2
The TF for activity A is: a.0 b.4 c.3 d.5 e.1 f.2
The LF for activity C is: a.6 b.7 c.8 d.9 e.10 f.11
The ES for activity D is: a.3 b.4 c.5 d.6 e.7 f.8
The LF for activity G is: a.10 b. 12 c.9 d.13 e.11 f.14 g.8
Assume /-day vvork Lalendar