Question: Answer the next three questions using the following information: Five critical path activities are candidates for crashing on a CPM network. Activity details are in
Answer the next three questions using the following information:
Five critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
| Activity | Normal Time | Normal Cost | Crash Duration | Crash Cost |
| A | 9 days | $8,000 | 7 days | $12,000 |
| B | 5 days | $2,000 | 3 days | $10,000 |
| C | 12 days | $9,000 | 10 days | $12,000 |
| D | 10 days | $10,000 | 9 days | $15,000 |
| E | 7 days | $6,000 | 7 days | $6,000 |
1. Which activity should be crashed first to cut one day from the project's duration?
2. Which activity should be the next activity crashed to cut a second day from the project's duration?
3. Assuming no other paths become critical, if the project is shortened to its maximum, how much cost will be added to the project.