Question: Answer. The order must arrive at work center 1 1 1 on day 1 2 6 . 5 . 1 8 . Back schedule the

Answer. The order must arrive at work center 111 on day 126.5.18. Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 200. Assume orders start at the beginning of a day and finish at the end of a day .