Question: ANSWER THE POINT D PLEASE? A project has the following estimated data: price = $69 per unit; variable costs = $35.19 per unit; fixed costs
ANSWER THE POINT D PLEASE?
A project has the following estimated data: price = $69 per unit; variable costs = $35.19 per unit; fixed costs = $7,000; required return = 15 percent; initial investment = $8,000; life = seven years. Ignore the effect of taxes. a. What is the accounting break-even quantity? Answer is complete and correct. 241 b. What is the cash break-even quantity? Answer is complete and correct. 207 c. What is the financial break-even quantity? Answer is complete but not entirely correct. 211 x d. What is the degree of operating leverage at the financial break-even level of output? Answer is complete but not entirely correct. 1.4659 X