Question: Answer the question 11 please 10. Calculating Project OCF Bush Boomerang, Inc., is considering a new three- year expansion project that requires an initial fixed

Answer the question 11 please
10. Calculating Project OCF Bush Boomerang, Inc., is considering a new three- year expansion project that requires an initial fixed asset investment of $2.1 mil- lion. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which time it will be worthless. The project is estimated to gener- ate $1,900,000 in annual sales, with costs of $850,000. If the tax rate is 35 per- cent, what is the OCF for this project? Calculating Project NPV In the previous problem, suppose the required re- turn on the project is 15 percent. What is the project's NPV? 11
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
