Question: answer them quickly and ill rate you. Calculator Lead Time Blues Inc, manufactures jeans in the cutting and sewing process Jeans are manufactured in 40-jean
Calculator Lead Time Blues Inc, manufactures jeans in the cutting and sewing process Jeans are manufactured in 40-jean batch sizes. The cutting time is 5 minutes per jean. The sewing time is 20 minutes per jean. It takes 2 minutes to move a batch of Jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process Value-added lead time minutes Non-value-added lead time minutes Total lead time minutes b. Compute the value-added ratio. Round to one decimal place. 20 we CH BH 5 6 7 8 9 O o U 7 T P G H K. L IL pa N M