Question: Answer this question with respect to the PERT problem posted in Canvas ( Test 1 0 Output document above ) . What is the variance

Answer this question with respect to the PERT problem posted in Canvas (Test 10 Output document above). What is the variance of task C?
Management Science
PERT OUTPUT : The following estimates of activity times (in days) are available for a small project.
\table[[Activity,Optimistic,Most Likely,Pessimistic],[A,4,5,6],[B,8,9,10],[C,7,7.5,11],[D,7,9,10],[E,6,7,9],[F,5,6,7]]
Answering the following questions first will give you an early start for your test.
a) Compute the expected completion time and variance for each activity.
b) An analyst has determined that the project's critical path consists of B-D-F. Compute the expected project completion time and standard deviation of project completion time.
c) What is the probability that the project will complete before 27 days?
 Answer this question with respect to the PERT problem posted in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!