Question: Any help would be appreciated to answer the question below for an investor analysis report. If additional information is needed, please let me know. Thanks

Any help would be appreciated to answer the question below for an investor analysis report. If additional information is needed, please let me know. Thanks in advance for any help!

Variances

Milestone Three - Variance Analysis

Data for Variance Analysis:

Budgeted (Standard) Hours/Qty

Budgeted (Standard) Rate

Actual Hours/Qty

Actual Rate

Labor

160

$ 16.00

180

$ 16.50

Materials

600

$ 9.10

660

$ 10.00

Variances for Collar Sales

Variance

Favorable/ Unfavorable

Direct Labor Time Variance

(Actual Hours - Standard Hours) x Standard Rate

$ 320.00

Unfavorable

Direct Labor Rate Variance

(Actual Rate - Standard Rate) x Actual Hours

$ 90.00

Unfavorable

Direct Materials Quantity/Efficiency Variance

(Actual Quantity - Standard Quantity) x Standard Price

$ 546.00

Unfavorable

Direct Materials Price Variance

(Actual Price - Standard Price) x Actual Quantity

$ 594.00

Unfavorable

[Illustrate the variances observed between the planned and actual values for the direct labor time and the direct materials price for collars. What changed?]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!