Question: AoA PERT Chart, Gentt Chart, and Microsoft Project a. [5 points] Draw {by hand) an ADA PERT chart of the project shown below. Take a

 AoA PERT Chart, Gentt Chart, and Microsoft Project a. [5 points]

AoA PERT Chart, Gentt Chart, and Microsoft Project a. [5 points] Draw {by hand) an ADA PERT chart of the project shown below. Take a snapshot of the chart and include it here. Be sure to provide a list of the tasks on the critical path and the project's duration. Also, identify the task with the greatest slack. Project Details: Activity Time (days! Immediate Predecessors A 9 - B 9 A C 2 A D 3 B E 3 B F 6 (1,10 G a E, F H 5 :1 I 7 F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!