Question: AON = Activity on node CPM = critical path method ES = earliest start EF = earliest finish LS = late start LF = late

AON = Activity on node
CPM = critical path method
ES = earliest start
EF = earliest finish
LS = late start
LF = late finish
For the project below: a. Construct an AON diagram. b. Construct a CPM network representation. c. Determine the ES, EF, LS, and LF times for the project. d. What is the critical path? e. How long will the project take to complete? f. What activity or activities should you crash to reduce the duration of the project by two weeks? g. Complete the critical path after deciding on this reduction. Crash Normal Additional cost to crash Activity Duration Predecessor Duration an activity (cost/week) (weeks) 1 1 1 2 3 2 2,000 1 3 2 1 3,000 2 4 4 3 1,000 2 5 2 1 500 3,4 6 1 1 5 7 4 3 5 2,500 5000 8 3 2 6,7 9 2 1 500 2 10 1 1 8,9Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
