Question: AON Network Activity ID Duration Precedence A 2 None B 3 None C 2 A D 4 A,B E 4 C F 3 C G

AON Network Activity ID Duration Precedence A 2 None B 3 None C 2 A D 4 A,B E 4 C F 3 C G 5 D,E H 2 F,G Crash Cost Table Activity Max Crash Time Crash Cost A 1 $ 22,750.00 B 1 $ 34,000.00 C 1 $ 27,000.00 D 3 $ 49,000.00 E 2 $ 58,000.00 F 2 $ 30,500.00 G 2 $ 84,500.00 H 1 $ 19,000.00 Current Cost of the Project is $ 308,000.00 Question: 1. Draw the AON network and determine the ES, EF, LS, LF, and SL. 2. Determine the current project length. 3. Crash the network as far as it can go and determine the cost for each time period crashed 4. Determine the final project cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!