Question: AON network diagram: Activity A B C D E F G H Normal Time (weeks) 5 3 6 3 5 7 4 4 Using the
AON network diagram:

| Activity | A | B | C | D | E | F | G | H |
| Normal Time (weeks) | 5 | 3 | 6 | 3 | 5 | 7 | 4 | 4 |
Using the information given, (a) Calculate the completion time for this project.
Project completion time = weeks.
(b) Identify the activities on the critical path.
Critical activities:
ABEGFD
ADFCEB
ACFGH
ADFGH
ACEGH
ABEGH
.