Question: AON Network Model in Excel: With the attached project data table (with monetary values in MGA), how can I create an AON network model in
AON Network Model in Excel: With the attached project data table (with monetary values in MGA), how can I create an AON network model in Excel? Please provide specific Excel formulas for calculating the Earliest Start Time, Earliest Finish Time, Latest Start Time, Latest Finish Time, Slack, and Critical Path for each activity. Also, include the method to calculate the Ki values for each activity, considering the monetary values are in MGA. Focus on practical Excel formulas and steps.
| Activity | Description | Predecessors | Duration (Weeks) | Accelerated (Weeks) | Resources (MGA) | Accelerated Cost (MGA) |
| A | Selection of Microcredit Office Location | None | 4 | 2 | 200000000 | 400000000 |
| B | Development of Organizational and Budgetary Plan | None | 6 | 3 | 150000000 | 300000000 |
| C | Human Resources Staffing Requirements | B | 4 | 2 | 70000000 | 140000000 |
| D | Physical Resources Office Design | A,C | 5 | 3 | 12000000 | 24000000 |
| E | Physical Resources Interior Construction | D | 9 | 4 | 25000000 | 50000000 |
| F | Human Resources Select Staff to Transfer | C | 3 | 2 | 12000000 | 24000000 |
| G | Human Resources Hire New Employees | F | 5 | 3 | 15000000 | 30000000 |
| H | Systems Assign Passwords/Codes | F | 3 | 2 | 3000000 | 6000000 |
| I | Tesoreria Apartar los recursos de acuerdo al presupuesto | B | 6 | 3 | 12000000 | 24000000 |
| J | Human Resources Train New Staff | E,G | 4 | 2 | 8000000 | 16000000 |
| K | Physical Resources Development of Advertising | I | 2 | 1 | 25000000 | 50000000 |
| L | Physical Resources Distribute Advertising to Media | K | 3 | 2 | 12000000 | 24000000 |
| M | Assignment of Responsibilities | J | 2 | 1 | 2000000 | 4000000 |
| N | Opening of New Office | M, H, I | 1 | 1 | 16000000 | 32000000 |