Question: Apple Company presents the following PERT-CPM data for certain project. (5 points) Activity Time in weeks Activity ABCDEFGH a) Construct a PERT Network. b)

Apple Company presents the following PERT-CPM data for certain project. (5 points) 

Apple Company presents the following PERT-CPM data for certain project. (5 points) Activity Time in weeks Activity ABCDEFGH a) Construct a PERT Network. b) Determine the critical path and slack time. 3 22ANAN WW 3 7 4 4 1 5 Preceding , AAABBUD C, E