Question: Appliances Incorporated is preparing an aggregate production plan for washers for the next four months. The company's expected monthly demand is given below in the

Appliances Incorporated is preparing an aggregate production plan for washers for the next four months. The company's expected monthly demand is given below in the chart. The company will have 650 washers in inventory at the beginning of the month and desires to maintain at least that number at the end of each month. Below are other critical data:
Beginning inventory 650
Desired minimum ending inventory at end of each month 650
Production cost per unit $360
Inventory carrying cost per month per unit (based on ending month inventory) $50
Hiring cost per worker $1,000
Firing cost per worker $2,000
Beginning number of workers 10
Each worker can produce (units per month)100
Required:
a. Given the planning information, develop a level production plan and a chase production plan.
Navigation:
Use the Open Excel in New Tab button to launch this question.
When finished in Excel, use the Save and Return to Assignment button in the lower right to return to Connect.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!