Question: Apply Burke ( 2 0 2 1 , 2 0 2 3 ) Critical Path Method, and calculate the Early Start, Early Finish, Late Finish,
Apply Burke Critical Path Method, and calculate the Early Start, Early Finish, Late Finish, Late Start and the Activity float for the project activities in the table below.
The project activities are:
Activity
Preceding Activity
Duration in Days
A
B
A
C
A
D
A
E
B
F
C
G
F
H
E G D
No marks will be awarded for calculations.
Ignore weekends and public holidays when designing a Gannt chart or when doing a network diagram to assist you with this question.
Accept a constant flow from the first day of the project to the last day.
Only enter the numeric amount for the Early Start, Early Finish, Late Finish, Late Start and for the Activity float.
marks
Activity
Early Start
Early Finish
Late Finish
Late Start
Activity Float
A
B
C
D
E
F
G
H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
